No completion certificate held
Thames Water says it holds no completion, handover or commissioning certificate for the capacity scheme.
We asked nineteen questions about Bourton-on-the-Water sewage treatment works. The response contains useful evidence, but most questions remain unresolved.
Thames Water responded on 10 September 2026 to our Environmental Information Regulations request.
The response includes some useful information. However, most of our nineteen questions remain unresolved.
The clearest answer confirms that Thames Water holds no completion, handover or commissioning certificate for the capacity scheme.
A supplied delay register forecasts construction completion in October 2027. Formal takeover is forecast for February 2028. This differs sharply from the published expectation of autumn 2026. The project was originally due for completion in 2023.
Other responses supplied different documents or data from those requested. Several questions received no direct answer. Two refusals cited no EIR exception or public-interest assessment.
The detailed record separates our questions, Thames Water's answers and SBSG's analysis. Readers can examine the evidence and reach their own conclusions.
These are SBSG's editorial categories. They are not legal findings or official determinations.
Thames Water says it holds no completion, handover or commissioning certificate for the capacity scheme.
The delay register forecasts October 2027 construction completion and February 2028 takeover.
The supplied level readings are not the requested event records. Their relationship to the public record is unclear.
Thames Water described a shift towards 2045–2050. It supplied no supporting decision record.
Open any question to compare Thames Water's response with our assessment and next question.
Thames Water described permitted values and final-effluent quality. It did not state the works' current flow-to-full-treatment capacity.
The response does not answer the question asked.
The capacity available today affects when storm overflow may occur.
Thames Water supplied programme L956.02, which concerns the phosphorus scheme.
The supplied programme does not appear to be the requested capacity-scheme programme.
A programme is needed to test published completion claims.
Thames Water states that it holds no completion, handover or commissioning certificates.
This directly answers the records question. It does not establish whether any element is already operating.
No supplied certificate demonstrates formal completion of the capacity scheme.
A delay register shows earlier February 2024 dates. It forecasts construction completion on 15 October 2027 and takeover on 29 February 2028. It records 109 early warnings and 23 maximum-risk items. An SSEN power diversion is identified as the main driver.
The register provides a valuable history of delay. Its dates differ sharply from the published autumn 2026 expectation.
The latest supplied forecast is years later than the original March 2023 target.
Thames Water referred to a national statutory target and a future limit of 0.4 milligrams per litre.
No WINEP reference, driver code or permit condition was supplied.
The formal obligation determines both the required outcome and its deadline.
Thames Water said the 0.4 milligrams-per-litre limit applies by March 2030. Its programme gives benefit delivery on 30 May 2030. The same material shows an Ofwat regulatory date of 31 March 2028.
The three dates are not reconciled.
Readers cannot judge programme compliance without one clear regulatory date.
Thames Water said several schemes remain active. It said each has its own completion criteria, but supplied no criteria.
The response gives context but withholds the definition requested.
Different meanings of completion can create misleading public dates.
Thames Water said no external completion date had been communicated and no relevant records were held.
That statement appears inconsistent with published GISMP dates, Thames Water's autumn 2026 webpage, and the supplied delay register.
Public statements should match internal programme evidence.
Thames Water supplied 122,612 sewer-level readings. These are not the requested discharge-event records. The series also contains gaps, including about 573 hours in 2023 and 48 hours in 2025.
The dataset may concern a different combined-sewer-overflow asset. Its relationship to the public Bourton STW record is unclear.
Event records are needed to check starts, stops and retrospective changes.
Thames Water linked to Defra guidance and described general quality checks. It said data is recorded at 15-minute intervals.
No Thames Water algorithm or validation process was supplied. Some provided readings occur at one-minute or two-minute intervals.
The calculation method matters when published stop times later appear different.
Thames Water described the procedure briefly but said the detailed document was for internal use only.
The response cites no EIR exception and includes no public-interest assessment.
A transparent amendment process protects trust in the public discharge record.
Thames Water said no spurious activations or exclusion labels were recorded in 2026.
That does not answer whether stop times were amended or whether an audit log exists.
An audit trail would allow observed changes to be checked fairly.
Thames Water said discharge volumes and quality are not monitored. It added that there is no regulatory requirement to monitor them.
The answer does not address whether volumes are estimated or modelled. The discharge point discussed is also unclear.
Duration alone cannot show the quantity or concentration released.
Thames Water referred to the GISMP appendices. It said no further infiltration work had been completed since publication in November 2025.
This provides a direct answer to the period covered.
Groundwater infiltration can consume sewer capacity and increase overflow pressure.
Thames Water supplied a narrative description but no calculation, model, report or verification record.
The basis for the stated 35 per cent and 50 per cent reductions remains untested.
Percentage claims need evidence if they influence future investment decisions.
Thames Water said the last GISMP update was November 2025 and updates are annual. It did not give the next publication date.
The answer also refers to the second Drainage and Wastewater Management Plan cycle, without confirming Bourton's future reporting route.
A clear update timetable lets the community track commitments and change.
Thames Water described a shift from 2035–2040 to 2045–2050.
No supporting decision record, analysis or programme document was supplied.
Moving the target by about a decade requires a clear evidential basis.
Thames Water supplied a programme whose cost columns contain zero values.
No budget line or funding value was provided.
A programme without visible funding cannot be assessed confidently.
Thames Water declined to provide information because later funding had not been agreed with regulators.
The response cites no EIR exception and includes no public-interest assessment.
The answer should distinguish between information not held and information being withheld.
The Word document contains every question, Thames Water's summarised response and our full analysis. It was prepared after SBSG reviewed the four supplied attachments.